Cheniere Energy Partners Reports Third Quarter 2013 Results
Houston, Texas - November 8, 2013 - Cheniere Energy Partners, L.P. (Cheniere Partners) (NYSE MKT: CQP) reported a net loss of $98.1 million and $196.9 million for the three and nine months ended September 30, 2013, respectively, compared to a net loss of $51.4 million and $106.8 million for the same periods in 2012, respectively.
Significant items for the three months and nine months ended September 30, 2013 were $23.8 million and $34.2 million, respectively, compared to $4.0 million and $38.0 million, respectively, for the comparable 2012 periods. Significant items for the quarter related to development expenses and derivative gains/losses, and for the nine months ended September 30, 2013, significant items also included loss on early extinguishment of debt. Development expenses were primarily for the liquefaction facilities we are developing through Sabine Pass Liquefaction, LLC (Sabine Pass Liquefaction) at the Sabine Pass LNG terminal adjacent to the existing regasification facilities (the "Liquefaction Project"). Derivative gains/losses were primarily the result of the change in fair value of Sabine Pass Liquefaction's interest rate derivatives to hedge the exposure to volatility in a portion of the floating-rate interest payments under the four credit facilities. Loss on early extinguishment of debt was related to Sabine Pass Liquefaction amending and replacing its $3.6 billion credit facility with four credit facilities aggregating $5.9 billion.
Liquefaction Project Update
We continue to make progress on the Liquefaction Project, which is being developed for up to six natural gas liquefaction trains ("Trains"), each with a design production of approximately 4.5 mtpa. We have received Federal Energy Regulatory Commission ("FERC") and Department of Energy ("DOE") approvals for Trains 1 through 4, and we have filed all required regulatory applications with the FERC and DOE to develop Trains 5 and 6.
The Trains are in various stages of development.
Construction on Trains 1 and 2 began in August 2012, and as of September 30, 2013, the overall project for Trains 1 and 2 was approximately 45% complete, which is ahead of the contracted schedule. Based on our current construction, we anticipate that Train 1 will produce LNG by late 2015.
Construction on Trains 3 and 4 began in May 2013, and as of September 30, 2013, the overall project for Trains 3 and 4 was approximately 10% complete. To date, soil stabilization has been completed and pile driving, our next critical path item, is underway. We expect Trains 3 and 4 to become operational in late 2016 and 2017, respectively.
We continue to make progress with the commercialization and development of Trains 5 and 6. To date, we have completed two LNG sale and purchase agreements (SPAs) for approximately 3.75 mtpa, in aggregate, of LNG volumes that commence with the start of Train 5 operations. Annual fixed fee revenues associated with these SPAs are approximately $0.6 billion. Bechtel has begun the front-end engineering design (FEED) on Trains 5 and 6, and we have commenced the regulatory approval process. In September 2013, we filed the complete application with the FERC. In February 2013 and in April 2013, we filed Free Trade Agreement ("FTA") and non-FTA export applications for LNG volumes under the SPAs with Total Gas & Power North America, Inc. (Total) and Centrica plc (Centrica), respectively. In September 2013, we filed FTA and non-FTA export applications for LNG volumes for the un-contracted volumes from Train 5 and for all volumes from Train 6. To date, we have received authorization from the DOE to export LNG volumes to FTA countries under the Total SPA and Centrica SPA. FTA authorization for the remaining volumes from Train 5 and all volumes from Train 6 as well as non-FTA authorizations for both Trains 5 and 6 are pending.













Liquefaction Project Timeline


 
 
Target Date
 
Milestone
 
Trains
1 & 2
 
Trains
3 & 4
 
Trains
5 & 6
 
DOE export authorization
 
Received
 
Received
 
T5: Received FTA
Pending Non-FTA
 
Definitive commercial agreements
 
Completed 7.7 mtpa
 
Completed 8.3 mtpa
 
T5: Completed
T6: 2014
 
- BG Gulf Coast LNG, LLC
 
4.2 mtpa
 
1.3 mtpa
 
 
 
- Gas Natural Fenosa
 
3.5 mtpa
 
 
 
 
 
- KOGAS
 
 
 
3.5 mtpa
 
 
 
- GAIL (India) Ltd.
 
 
 
3.5 mtpa
 
 
 
- Total Gas & Power N.A.
 
 
 
 
 
2.0 mtpa
 
- Centrica plc
 
 
 
 
 
1.75 mtpa
 
EPC contract
 
Completed
 
Completed
 
2015
 
Financing
 
 
 
 
 
2015
 
- Equity
 
Completed
 
Completed 
 
 
 
- Debt commitments
 
Received
 
 Received
 
 
 
FERC authorization
 
 
 
 
 
 
 
- FERC Order
 
Received
 
Received
 
2015
 
- Certificate to commence construction
 
Received
 
Received
 
 
 
Issue Notice to Proceed
 
Completed
 
Completed
 
2015
 
Commence operations
 
2015/2016
 
2016/2017
 
2018/2019
 

Q3 2013 Results
For the quarter and nine months ended September 30, 2013, Cheniere Partners reported loss from operations of $23.4 million and $38.1 million, respectively, compared to loss of $8.2 million and income of $23.7 million for the respective comparable periods in 2012. Net operating losses were primarily affected by operating and maintenance expenses and general and administrative expenses. Increases in operating and maintenance expenses of $15.8 million and $41.7 million for the three and nine months ended September 30, 2013, respectively, compared to the comparable 2012 periods resulted primarily from costs incurred to purchase LNG to maintain the cryogenic readiness of the regasification facilities at the Sabine Pass LNG terminal and for the nine months ended September 30, 2013, included increases in variable compensation expenses. Increases in general and administrative expenses of $3.3 million and $52.5 million for the three and nine months ended September 30, 2013, respectively, compared to the comparable 2012 periods were primarily due to increased costs incurred to manage the construction of Trains 1 through 4, which resulted from a management services agreement entered into by Sabine Pass Liquefaction, in which Sabine Pass Liquefaction is required to pay a wholly owned subsidiary of Cheniere Energy, Inc. (Cheniere Energy) a monthly fee based upon the capital expenditures incurred in the previous month for the Liquefaction Project. For the three and nine months ended September 30, 2013, the costs incurred to manage the construction of Trains 1 through 4 were $35.2 million and $72.9 million, respectively. These payments are being funded from proceeds received from the Liquefaction Project's equity and debt financings.
2013 Distributions
We estimate that the annualized distribution to common unitholders for fiscal year 2013 will be $1.70 per unit. We will pay a cash distribution per common unit of $0.425 to unitholders of record as of November 1, 2013, and the related general partner distribution on November 14, 2013.






Cheniere Partners owns 100 percent of the Sabine Pass LNG terminal located on the Sabine Pass deep water shipping channel less than four miles from the Gulf Coast.  The Sabine Pass LNG terminal has regasification facilities that include existing infrastructure of five LNG storage tanks with capacity of approximately 16.9 billion cubic feet equivalent (Bcfe), two docks that can accommodate vessels with capacity of up to 265,000 cubic meters and vaporizers with regasification capacity of approximately 4.0 Bcf/d.  Cheniere Partners is developing natural gas liquefaction facilities at the Sabine Pass LNG terminal adjacent to the existing regasification facilities (the "Liquefaction Project"). Cheniere Partners plans to construct over time up to six natural gas liquefaction trains (Trains), which are in various stages of development. Each Train is expected to have a design production capacity of approximately 4.5 mtpa.  Cheniere Partners' wholly owned subsidiary, Sabine Pass Liquefaction, LLC (Sabine Pass Liquefaction), has entered into lump sum turnkey contracts for the engineering, procurement and construction of Train 1, Train 2, Train 3 and Train 4 with Bechtel Oil, Gas and Chemicals, Inc. ("Bechtel").  Sabine Pass Liquefaction has commenced construction of Train 1 and Train 2 and the related new facilities needed to treat, liquefy, store and export natural gas. Construction of Train 3 and Train 4 and the related facilities commenced in May 2013. Sabine Pass Liquefaction recently began the development of Train 5 and Train 6 and commenced the regulatory process in February 2013. Sabine Pass Liquefaction has also entered into six third-party LNG sale and purchase agreements ("SPAs"). The customers include BG Gulf Coast LNG, LLC ("BG") for 5.5 mtpa, Gas Natural Aprovisionamientos SDG S.A. ("Gas Natural Fenosa") for 3.5 mtpa, Korea Gas Corporation ("KOGAS") for 3.5 mtpa, GAIL (India) Ltd. ("GAIL") for 3.5 mtpa, Total Gas & Power North America, Inc. ("Total") for 2.0 mtpa and Centrica plc (Centrica) for 1.75 mtpa.  In addition, Sabine Pass Liquefaction has entered into an SPA with Cheniere Marketing, LLC ("Cheniere Marketing") for up to 2.0 mtpa of LNG that is produced but not already committed to third parties. The BG and Cheniere Marketing SPAs commence with the start of Train 1 operations and the Gas Natural Fenosa SPA commences with the start of Train 2 operations.  The KOGAS and GAIL SPAs commence with the start of Train 3 and Train 4 operations, respectively, and the Total and Centrica SPAs commence with the start of Train 5 operations. Cheniere Partners has placed documentation pertaining to the Liquefaction Project, including the applications and supporting studies, on its website located at http://www.cheniereenergypartners.com.
For additional information, please refer to the Cheniere Energy Partners, L.P. website at www.cheniereenergypartners.com and Quarterly Report on Form 10-Q for the period ended September 30, 2013, filed with the Securities and Exchange Commission.
This press release contains certain statements that may include "forward-looking statements" within the meanings of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. All statements, other than statements of historical facts, included herein are "forward-looking statements." Included among "forward-looking statements" are, among other things, (i) statements regarding Cheniere Partners' business strategy, plans and objectives, including the construction and operation of liquefaction facilities, (ii) statements regarding our expectations regarding regulatory authorizations and approvals, (iii) statements expressing beliefs and expectations regarding the development of Cheniere Partners' LNG terminal and liquefaction business, (iv) statements regarding the business operations and prospects of third parties, (v) statements regarding potential financing arrangements, and (vi) statements regarding future discussions and entry into contracts. Although Cheniere Partners believes that the expectations reflected in these forward-looking statements are reasonable, they do involve assumptions, risks and uncertainties, and these expectations may prove to be incorrect. Cheniere Partners' actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in Cheniere Partners' periodic reports that are filed with and available from the Securities and Exchange Commission. You should not place undue reliance on these forward-looking statements, which speak only as of the date of this press release. Other than as required under the securities laws, Cheniere Partners does not assume a duty to update these forward-looking statements.



 (Financial Table Follows)






Cheniere Energy Partners, L.P.
Selected Financial Information
(in thousands, except per unit data) (1) 

 
 
Three Months Ended
 
Nine Months Ended
 
 
September 30,
 
September 30,
 
 
2013
 
2012
 
2013
 
2012
Revenues
 
 
 
 
 
 
 
 
Revenues
 
$
66,646

 
$
62,429

 
$
199,052

 
$
190,160

Revenues—affiliate
 
800

 
3,929

 
2,140

 
6,973

Total revenues
 
67,446

 
66,358

 
201,192

 
197,133

 
 
 
 
 
 
 
 
 
Expenses
 
 

 
 

 
 
 
 
Operating and maintenance expense
 
23,553

 
6,395

 
52,751

 
20,063

Operating and maintenance expense—affiliate
 
6,314

 
7,711

 
23,534

 
14,486

Depreciation expense
 
14,491

 
14,489

 
43,150

 
43,135

Development expense
 
1,355

 
4,229

 
8,157

 
35,369

Development expense—affiliate
 
133

 
102

 
1,195

 
2,365

General and administrative expense
 
2,718

 
4,737

 
8,521

 
9,235

General and administrative expense—affiliate
 
42,239

 
36,871

 
101,998

 
48,745

Total expenses
 
90,803

 
74,534

 
239,306

 
173,398

 
 
 
 
 
 
 
 
 
Income (loss) from operations
 
(23,357
)
 
(8,176
)
 
(38,114
)
 
23,735

 
 
 
 
 
 
 
 
 
Other income (expense)
 
 

 
 

 
 
 
 
Interest expense, net
 
(52,528
)
 
(43,626
)
 
(134,806
)
 
(130,554
)
Loss on early extinguishment of debt
 

 

 
(80,510
)
 

Derivative gain (loss), net
 
(22,335
)
 
287

 
55,706

 
(288
)
Other
 
111

 
145

 
873

 
289

Total other expense
 
(74,752
)
 
(43,194
)
 
(158,737
)
 
(130,553
)
 
 
 
 
 
 
 
 
 
Net loss
 
$
(98,109
)
 
$
(51,370
)
 
$
(196,851
)
 
$
(106,818
)
 
 
 
 
 
 
 
 
 
Basic and diluted net income (loss) per common unit
 
$
(0.20
)
 
$
0.04

 
$
(0.01
)
 
$
0.36

 
 
 
 
 
 
 
 
 
Weighted average number of common units outstanding used for basic and diluted net income per common unit calculation
 
57,079

 
31,997

 
53,277

 
31,449








 
September 30, 2013
 
December 31, 2012
Cash and cash equivalents
$
339,895

 
$
419,292

Restricted cash and cash equivalents
210,076

 
92,519

LNG inventory
14,158

 
2,625

Other current assets (2)
59,090

 
18,687

Non-current restricted cash and cash equivalents
828,360

 
272,425

Property, plant and equipment, net
5,642,872

 
3,219,592

Debt issuance costs, net
340,856

 
220,949

Non-current derivative assets
64,309

 

Other assets
71,102

 
19,698

Total assets
$
7,570,718

 
$
4,265,787

 
 
 
 
Current liabilities (2)
$
233,878

 
155,836

Long-term debt, net of discount
5,574,195

 
2,167,113

Deferred revenue, including affiliate
35,673

 
36,220

Long-term derivative liability

 
26,424

Other liabilities (2)
1,209

 
216

Total partners' capital
1,725,763

 
1,879,978

Total liabilities and partners' capital
$
7,570,718

 
$
4,265,787

 
 
 
 
 
(1)
Please refer to the Cheniere Energy Partners, L.P. Quarterly Report on Form 10-Q for the period ended September 30, 2013, filed with the Securities and Exchange Commission.
(2)
Amounts include transactions between Cheniere Energy Partners, L.P. and Cheniere Energy, Inc. or subsidiaries of Cheniere Energy, Inc.


CONTACTS:
Investors: Christina Burke: 713-375-5104, Nancy Bui: 713-375-5280
Media: Diane Haggard: 713-375-5259