• | First LNG commissioning cargo exported in February marking transition towards operations |
• | In February, the first commissioning cargo with LNG produced at the Sabine Pass Liquefaction Project (defined below) was successfully loaded and exported. A total of four LNG commissioning cargoes were loaded and exported during the three months ended March 31, 2016, and a total of seven LNG commissioning cargoes have been loaded and exported to date. |
• | In February, Cheniere Partners closed on up to approximately $2.8 billion of senior secured credit facilities (the “CQP Credit Facilities”). The four-year credit facilities consist of a $450 million CTPL tranche term loan, an approximately $2.1 billion Sabine Pass LNG, L.P. (“SPLNG”) tranche term loan, a $125 million debt service reserve credit facility, and a $115 million revolving credit facility. The CTPL tranche term loan was used to prepay the $400 million senior secured term loan at CTPL subsequent to closing of the facilities. Remaining proceeds from the facilities will be used by Cheniere Partners (i) to redeem or repay the approximately $1.7 billion senior secured notes due 2016 and the $420 million senior secured notes due 2020 that were issued by SPLNG, (ii) to pay associated transaction costs and make-whole amounts, if any, and (iii) for general business purposes of Cheniere Partners and its subsidiaries. |
▪ | Construction on Trains 1 and 2 began in August 2012, and as of March 31, 2016, the overall project completion percentage for Trains 1 and 2 was approximately 98.3%, which is ahead of the contractual schedule. We expect substantial completion of Train 1 to be achieved in May 2016. The commissioning process on Train 2 has commenced, and we expect substantial completion of Train 2 to be achieved in September 2016. |
▪ | Construction on Trains 3 and 4 began in May 2013, and as of March 31, 2016, the overall project completion percentage for Trains 3 and 4 was approximately 83.8%, which is ahead of the contractual schedule. We expect Trains 3 and 4 to reach substantial completion in 2017. |
▪ | Construction on Train 5 began in June 2015, and as of March 31, 2016, the overall project completion percentage for Train 5 was approximately 28.8%, which is ahead of the contractual schedule. Engineering, procurement, subcontract work and Bechtel direct hire construction were approximately 59.1%, 45.1%, 24.2% and 0.4% complete, respectively. We expect Train 5 to reach substantial completion in 2019. |
▪ | Train 6 is currently under development, with all necessary regulatory approvals in place. We expect to make a final investment decision and commence construction on Train 6 upon, among other things, entering into an EPC contract, entering into acceptable commercial arrangements and obtaining adequate financing. |
Sabine Pass Liquefaction Project | ||||
Liquefaction Train | Train 1 | Train 2 | Trains 3-4 | Train 5 |
Project Status | Commissioning / Producing LNG | Commissioning | 84% Overall Completion | 29% Overall Completion |
Expected Substantial Completion | 1H 2016 | 2H 2016 | 2017 | 2019 |
Three Months Ended | |||||||
March 31, | |||||||
2016 | 2015 | ||||||
Revenues | |||||||
Regasification revenues | $ | 65,384 | $ | 66,718 | |||
Regasification revenues—affiliate | 1,635 | 812 | |||||
LNG revenues | — | — | |||||
Other revenues | 28 | — | |||||
Total revenues | 67,047 | 67,530 | |||||
Operating costs and expenses | |||||||
Cost of sales (excluding depreciation and amortization expense shown separately below) | 3,904 | 693 | |||||
Operating and maintenance expense | 17,385 | 30,540 | |||||
Operating and maintenance expense—affiliate | 10,830 | 4,773 | |||||
Development expense | 66 | 1,151 | |||||
Development expense—affiliate | 129 | 204 | |||||
General and administrative expense | 2,610 | 3,515 | |||||
General and administrative expense—affiliate | 22,198 | 21,597 | |||||
Depreciation and amortization expense | 19,388 | 14,879 | |||||
Total operating costs and expenses | 76,510 | 61,780 | |||||
Loss from operations | (9,463 | ) | 5,750 | ||||
Other income (expense) | |||||||
Interest expense, net of amounts capitalized | (43,452 | ) | (42,845 | ) | |||
Loss on early extinguishment of debt | (1,457 | ) | (88,992 | ) | |||
Derivative loss, net | (20,808 | ) | (37,138 | ) | |||
Other income | 274 | 121 | |||||
Total other expense | (65,443 | ) | (168,854 | ) | |||
Net loss | $ | (74,906 | ) | $ | (163,104 | ) | |
Basic and diluted net loss per common unit | $ | (0.08 | ) | $ | (0.61 | ) | |
Weighted average number of common units outstanding used for basic and diluted net loss per common unit calculation | 57,084 | 57,080 |
(1) | Please refer to the Cheniere Energy Partners, L.P. Quarterly Report on Form 10-Q for the quarter ended March 31, 2016, filed with the Securities and Exchange Commission. |
March 31, | December 31, | ||||||
2016 | 2015 | ||||||
ASSETS | (unaudited) | ||||||
Current assets | |||||||
Cash and cash equivalents | $ | 9,815 | $ | 146,221 | |||
Restricted cash | 401,972 | 274,557 | |||||
Accounts receivable—affiliate | 14,544 | 1,271 | |||||
Advances to affiliate | 29,356 | 39,836 | |||||
Inventory | 28,543 | 16,667 | |||||
Other current assets | 17,986 | 14,923 | |||||
Total current assets | 502,216 | 493,475 | |||||
Non-current restricted cash | 13,650 | 13,650 | |||||
Property, plant and equipment, net | 12,713,379 | 11,931,602 | |||||
Debt issuance costs, net | 172,959 | 132,091 | |||||
Non-current derivative assets | 28,210 | 30,304 | |||||
Other non-current assets | 220,631 | 232,031 | |||||
Total assets | $ | 13,651,045 | $ | 12,833,153 | |||
LIABILITIES AND PARTNERS’ EQUITY | |||||||
Current liabilities | |||||||
Accounts payable | $ | 17,131 | $ | 16,407 | |||
Accrued liabilities | 332,288 | 224,292 | |||||
Current debt, net | 1,785,318 | 1,673,379 | |||||
Due to affiliates | 78,159 | 115,123 | |||||
Deferred revenue | 26,669 | 26,669 | |||||
Deferred revenue—affiliate | 717 | 717 | |||||
Derivative liabilities | 11,818 | 6,430 | |||||
Other current liabilities | 93 | — | |||||
Total current liabilities | 2,252,193 | 2,063,017 | |||||
Long-term debt, net | 10,734,069 | 10,018,325 | |||||
Non-current deferred revenue | 8,500 | 9,500 | |||||
Non-current derivative liabilities | 16,210 | 2,884 | |||||
Other non-current liabilities | 172 | 175 | |||||
Other non-current liabilities—affiliate | 26,632 | 26,321 | |||||
Partners’ equity | |||||||
Common unitholders’ interest (57.1 million units issued and outstanding at March 31, 2016 and December 31, 2015) | 259,168 | 305,747 | |||||
Class B unitholders’ interest (145.3 million units issued and outstanding at March 31, 2016 and December 31, 2015) | (35,588 | ) | (37,429 | ) | |||
Subordinated unitholders’ interest (135.4 million units issued and outstanding at March 31, 2016 and December 31, 2015) | 375,104 | 428,035 | |||||
General partner’s interest (2% interest with 6.9 million units issued and outstanding at March 31, 2016 and December 31, 2015) | 14,585 | 16,578 | |||||
Total partners’ equity | 613,269 | 712,931 | |||||
Total liabilities and partners’ equity | $ | 13,651,045 | $ | 12,833,153 |
(1) | Please refer to the Cheniere Energy Partners, L.P. Quarterly Report on Form 10-Q for the quarter ended March 31, 2016, filed with the Securities and Exchange Commission. |