PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00033 DATE OF CHANGE ORDER: May 24, 2018 |
1. | Per Article 6.1.B of the Agreement, the Parties agree Contractor shall develop inspection piping isometrics to facilitate system inspections. The inspection piping isometrics are to be developed within six months following approval of this Change Order. |
2. | The work pursuant to this Change Order is not a condition to and will not prevent the achievement of Stage 3 Substantial Completion or impact the Stage 3 Defect Correction Period. |
3. | The cost breakdown for this Change Order is detailed in Exhibit A. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
The original Contract Price was........................................................................................................................ | $ | 2,987,000,000 | |
Net change by previously authorized Change Orders (#00001-00032)............................................................ | $ | 105,739,177 | |
The Contract Price prior to this Change Order was.......................................................................................... | $ | 3,092,739,177 | |
The Contract Price will be increased by this Change Order in the amount of.................................................. | $ | 879,340 | |
The new Contract Price including this Change Order will be.......................................................................... | $ | 3,093,618,517 |
/s/ Ed Lehotsky | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
Ed Lehotsky | Bhupesh Thakkar | |
Name | Name | |
SVP LNG E&C | Senior Project Manager | |
Title | Title | |
June 8, 2018 | May 24, 2018 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00034 DATE OF CHANGE ORDER: May 31, 2018 |
1. | Per Article 6.1.B of the Agreement, the Parties agree Owner shall pay Contractor Three Hundred Eleven Thousand Nine U.S. Dollars (U.S. $311,009) for craft and field non-manual costs incurred during the Site evacuation on April 26, 2018. The Site evacuation was in response to an emergency event in the Existing Facility. |
2. | The cost breakdown for this Change Order is detailed in Exhibit A. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
The original Contract Price was........................................................................................................................ | $ | 2,987,000,000 | |
Net change by previously authorized Change Orders (#00001-00033)............................................................ | $ | 106,618,517 | |
The Contract Price prior to this Change Order was.......................................................................................... | $ | 3,093,618,517 | |
The Contract Price will be increased by this Change Order in the amount of.................................................. | $ | 311,009 | |
The new Contract Price including this Change Order will be.......................................................................... | $ | 3,093,929,526 |
/s/ Ed Lehotsky | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
Ed Lehotsky | Bhupesh Thakkar | |
Name | Name | |
SVP LNG E&C | Senior Project Manager | |
Title | Title | |
June 19, 2018 | May 31, 2018 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00035 DATE OF CHANGE ORDER: June 7, 2018 |
1. | Change Order CO-00020, dated March 29, 2017, increased the Existing & Stages 1 and 2 Liquefaction Facility Labor Provisional Sum specified in Article 2.2 of Attachment EE, Schedule EE-2 of the Stage 3 Agreement to U.S. $57,307,342 and 415,131 hours. This Change Order decreases the Existing & Stages 1 and 2 Liquefaction Facility Labor Provisional Sum by $33,007,589 and 225,357 hours. The new Existing & Stages 1 and 2 Liquefaction Facility Labor Provisional Sum is Twenty-Four Million, Two Hundred Ninety-Nine Thousand, Seven Hundred Fifty-Three U.S. Dollars ($24,299,753) and 189,774 hours. |
2. | The Aggregate Provisional Sum specified in Article 7.1A of the Agreement prior to this Change Order was $324,346,437. This Change Order decreases the Aggregate Provisional Sum amount by $33,007,589 resulting in a new value is $291,338,848. |
3. | The cost breakdown for this Change Order is detailed in Exhibit A. |
4. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit B of this Change Order. |
The original Contract Price was........................................................................................................................ | $ | 2,987,000,000 | |
Net change by previously authorized Change Orders (#00001-00034)............................................................ | $ | 106,929,526 | |
The Contract Price prior to this Change Order was.......................................................................................... | $ | 3,093,929,526 | |
The Contract Price will be increased by this Change Order in the amount of.................................................. | $ | (33,007,589 | ) |
The new Contract Price including this Change Order will be.......................................................................... | $ | 3,060,921,937 |
/s/ Ed Lehotsky | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
Ed Lehotsky | Bhupesh Thakkar | |
Name | Name | |
SVP LNG E&C | Senior Project Manager | |
Title | Title | |
June 19, 2018 | June 7, 2018 | |
Date of Signing | Date of Signing |
PROJECT NAME: Sabine Pass LNG Stage 3 Liquefaction Facility OWNER: Sabine Pass Liquefaction, LLC CONTRACTOR: Bechtel Oil, Gas and Chemicals, Inc. DATE OF AGREEMENT: May 4, 2015 | CHANGE ORDER NUMBER: CO-00036 DATE OF CHANGE ORDER: June 7, 2018 |
1. | Per Article 6.1.B of the Agreement, Parties agree Contractor will provide Owner the General Electric, instrument and valve spare parts and tools listed in Exhibit A. |
2. | The cost breakdown for this Change Order is detailed in Exhibit B. |
3. | Schedule C-1 (Milestone Payment Schedule) of Attachment C of the Agreement will be amended by including the milestone(s) listed in Exhibit C of this Change Order. |
The original Contract Price was........................................................................................................................ | $ | 2,987,000,000 | |
Net change by previously authorized Change Orders (#00001-00035)............................................................ | $ | 73,921,937 | |
The Contract Price prior to this Change Order was.......................................................................................... | $ | 3,060,921,937 | |
The Contract Price will be increased by this Change Order in the amount of.................................................. | $ | 536,563 | |
The new Contract Price including this Change Order will be.......................................................................... | $ | 3,061,458,500 |
/s/ Ed Lehotsky | /s/ Bhupesh Thakkar | |
Owner | Contractor | |
Ed Lehotsky | Bhupesh Thakkar | |
Name | Name | |
SVP LNG E&C | Senior Project Manager | |
Title | Title | |
June 19, 2018 | June 7, 2018 | |
Date of Signing | Date of Signing |