Supplemental Cash Flow Information SUPPLEMENTAL CASH FLOW INFORMATION
 
The following table provides supplemental disclosure of cash flow information (in millions):
Three Months Ended March 31,
2022 2021
Cash paid during the period for interest on debt, net of amounts capitalized $ 161  $ 185 
Non-cash investing and financing activities:
Property, plant and equipment, net of accumulated depreciation funded with accounts payable and accrued liabilities (including affiliate) 386  229 
Novation of IPM agreement from Cheniere Corpus Christi Liquefaction Stage III, LLC (“CCL Stage III”)
(2,712) — 
Novation of IPM Agreement from CCL Stage III
In March 2022, in connection with a prior commitment from Cheniere to collateralize financing for Train 6 of the Liquefaction Project, SPL and CCL Stage III, a wholly owned subsidiary of Cheniere, entered into an agreement to assign to SPL an IPM agreement to purchase 140,000 MMBtu per day of natural gas at a price based on the Platts Japan Korea Marker (“JKM”), for a term of approximately 15 years beginning in early 2023. The transaction has been accounted for as a transfer between entities under common control, which required us to recognize the obligations assumed at the historical basis of Cheniere. Upon the transfer, which occurred on March 15, 2022, we recognized $2.7 billion in distributions to Cheniere’s common unitholder interest within our Consolidated Statements of Partners’ Equity (Deficit) based on our assumption of current derivative liabilities and derivative liabilities of $0.1 billion and $2.6 billion, respectively.