Annual report pursuant to Section 13 and 15(d)

Deferred Revenue

v2.4.0.8
Deferred Revenue
12 Months Ended
Dec. 31, 2013
Deferred Revenue [Abstract]  
Deferred Revenue
DEFERRED REVENUE
 
Advance Capacity Reservation Fee

In November 2004, Total paid Sabine Pass LNG a nonrefundable advance capacity reservation fee of $10.0 million in connection with the reservation of approximately 1.0 Bcf/d of LNG regasification capacity at the Sabine Pass LNG terminal. An additional advance capacity reservation fee payment of $10.0 million was paid by Total to Sabine Pass LNG in April 2005. The advance capacity reservation fee payments are being amortized as a reduction of Total's regasification capacity reservation fee under its TUA over a 10-year period beginning with the commencement of its TUA on April 1, 2009. As a result, we recorded the advance capacity reservation fee payments that Sabine Pass LNG received, although non-refundable, as deferred revenue to be amortized to income over the corresponding 10-year period.

In November 2004, Sabine Pass LNG also entered into a TUA to provide Chevron U.S.A. Inc. ("Chevron") with approximately 0.7 Bcf/d of LNG regasification capacity at the Sabine Pass LNG terminal. In December 2005, Chevron exercised its option to increase its reserved capacity by approximately 0.3 Bcf/d to approximately 1.0 Bcf/d, making advance capacity reservation fee payments to Sabine Pass LNG totaling $20.0 million. The advance capacity reservation fee payments are being amortized as a reduction of Chevron's regasification capacity reservation fee under its TUA over a 10-year period beginning with the commencement of its TUA on July 1, 2009. As a result, we recorded the advance capacity reservation fee payments that Sabine Pass LNG received, although non-refundable, as deferred revenue to be amortized to income over the corresponding 10-year period.

As of December 31, 2013, we had recorded $4.0 million and $17.5 million as current and non-current deferred revenue on our Consolidated Balance Sheets, respectively, related to the Total and Chevron advance capacity reservation fees. As of December 31, 2012, we had recorded $4.0 million and $21.5 million as current and non-current deferred revenue on our Consolidated Balance Sheets, respectively, related to the Total and Chevron advance capacity reservation fees.

TUA Payments

Following the achievement of commercial operability of the Sabine Pass LNG terminal in September 2008, Sabine Pass LNG began receiving capacity reservation fee payments from Cheniere Marketing under its TUA. Effective July 1, 2010, Cheniere Marketing assigned its existing TUA with Sabine Pass LNG to Cheniere Energy Investments, LLC ("Cheniere Investments"), including all of its rights, titles, interests, obligations and liabilities in and under the TUA. Sabine Pass Liquefaction obtained this reserved capacity as a result of an assignment in July 2012 by Cheniere Investments of its rights, title and interest under its TUA. In connection with the assignment, Sabine Pass LNG, Sabine Pass Liquefaction and Cheniere Investments entered into a terminal use rights assignment and agreement ("TURA") pursuant to which Cheniere Investments has the right to use Sabine Pass Liquefaction's reserved capacity under the TUA and has the obligation to make the monthly capacity payments required by the TUA to Sabine Pass LNG. Cheniere Investments' right to use capacity at the Sabine Pass LNG terminal will be reduced as each of Trains 1 through 4 reaches commercial operation. The percentage of the monthly capacity payments payable by Cheniere Investments will be reduced from 100% to zero (unless Cheniere Investments utilizes terminal use capacity after Train 4 reaches commercial operations), and the percentage of the monthly capacity payments payable by us will increase by the amount that Cheniere Investments' percentage decreases. We have guaranteed Sabine Pass Liquefaction's obligations under its TUA and the obligations of Cheniere Investments under its TURA. However, the revenue earned by Sabine Pass LNG from capacity payments by Cheniere Investments under its TUA was eliminated and under its TURA is eliminated upon consolidation of our financial statements. As a result, we have zero current deferred revenue—affiliate related to Cheniere Investments' monthly advance capacity reservation fee payment as of December 31, 2013 and 2012.

Total and Chevron are obligated to make monthly TUA payments to Sabine Pass LNG in advance of the month of service. These monthly payments are recorded to current deferred revenue in the period cash is received and are then recorded as revenue in the next month when the TUA service is performed. As of December 31, 2013 and 2012, we had recorded $21.2 million and $21.1 million, respectively, as current deferred revenue on our Consolidated Balance Sheets related to Total's and Chevron's monthly TUA payments.